Project Description:This project will improve the pavement along SW 62nd Boulevard by providing a new asphalt surface from SW 20th Avenue to State Road 26 (SR 26/Newberry Road). Also included will be new 5-foot wide paved shoulders along both sides of the roadway through existing areas of unpaved grass shoulders. Approximate total length of this improvement is 1 ½ miles.
Project Update: 8/4/2020
Design plans have been completed. Construction is anticipated to begin Spring of 2021.
Project Update:Project is currently in the design phase and the City has received 60% Plans. Final plans are scheduled for completion in May, 2019. Construction is planned for the summer of 2019.
Contact Information:
Project Manager – Louis Brunetti
Email: BrunettiLR@cityofgainesville.org
Phone: 352-393-8405