SW 62nd Blvd Roadway

Project Description:This project will improve the pavement along SW 62nd Boulevard by providing a new asphalt surface from SW 20th Avenue to State Road 26 (SR 26/Newberry Road).  Also included will be new 5-foot wide paved shoulders along both sides of the roadway through existing areas of unpaved grass shoulders.  Approximate total length of this improvement is 1 ½ miles. 

Project Update: 8/4/2020

Design plans have been completed. Construction is anticipated to begin Spring of 2021.

Project Update:Project is currently in the design phase and the City has received 60% Plans.  Final plans are scheduled for completion in May, 2019.  Construction is planned for the summer of 2019. 

Contact Information:

Project Manager – Louis Brunetti

Email:  BrunettiLR@cityofgainesville.org

Phone:  352-393-8405