Project Description: Construction of new roadway connecting Archer Road to SW 34th St at SW 47th Ave. Roadway cross-section includes 2-lanes, bicycle lanes and sidewalks.
Project Update : 9/25/2019
Project completed. Ribbon cutting scheduled for October 22, 2019.
Project Update : 4/1/2019
The project was awarded to Commercial Industrial Corporation for construction. The work is anticipated to be completed in Summer 2019.
Contact Information:
Project Manager –Matt Williams
WilliamsRM@cityofgainesville.org
352-393-8416