SW 16th Terr Roadway

Project Description:

This project will mill and resurface NW 16th Terrace from NW 16th Avenue to NW 23rd Avenue.  All existing asphalt will be milled and resurfaced with new asphalt. The scope of work also includes replacing the existing school zone signs with new signs with solar powered flashing beacons.  Improvements to the pavement markings and new signage is also included.     

Project Update: 8/4/2020

All work is complete.

Project Update : 2/28/2020

Project substantially completed. Final completion scheduled for February 28, 2020.

Project Update : 7/23/2019

Construction work is progressing as scheduled.  Southbound lane was paved July 22, 2019, and the Northbound lane will be paved July 23, 2019.  Signs and the new School Zone flashing beacons will be installed after the road is resurfaced and flashing beacons delivered.

Project Update: 7/11/2019

A Pre-Construction meeting was held with the Contractor on July 10, 2019 to review final plans prior to starting construction.  Message Boards and Construction signs will be installed and completed by July 16th   with milling and resurfacing scheduled to start on Friday, July 19th.  The milling and resurfacing is scheduled for completion by August 1st, with remaining work substantially complete by August 9th.

Contact Information:

Project Manager – Louis Brunetti

Email:  BrunettiLR@cityofgainesville.org

Phone:  352-393-8405