SE 2nd Avenue & SE 7th Street Roundabout

IMG_0316This project consists of a proposed roundabout at the intersection of SE 2nd Avenue and SE 7th Street. The project includes modification of existing medians and horizontal alignment at the intersection. Landscape, hardscape, lighting and sidewalk improvements are also included within the scope of work.

Design: JMJ Consulting Engineering
Contract Amount: $30,712 (includes subcontractors)

Construction: TBD
Contract Amount: $180,000 (Estimated)

Schedule: Construction currently not funded.

Progress: Construction plans completed. Funding for construction has yet to be secured.

Project Manager
Rick Melzer, P.E.
(352) 393-8407
melzerra@cityofgainesville.org

Comments are closed.