NW 23rd Terrace Sidewalk/NW 34th Blvd

NW 23rd Terrace Sidewalk

Purpose: Construct a new sidewalk on the west side of NW 23rd Terrace connecting NW 62nd Avenue to the newly installed sidewalk in front of Walmart on NW 34th Boulevard.  This project will also include modifications to existing RTS bus stops for ADA compliance.

Design: JMJ Consulting Engineering

Construction: Funded

Schedule: Construction began in October 2015.

Progress:
–Utility upgrades were completed in March 2014.
–Plans are being revised to incorporate utilities as-built and job will be ready to bid by the end of the third quarter of FY14.

Project Manager 
Debbie Leistner
(352) 393-8412
leistnerdl@cityofgainesville.org